Projects
Offshore wind farms
One row per farm. Kept when an install window is dated and a package is still open or unknown. Blank = not disclosed.
23 of 23
Baltic Power ORLEN / Northland Power | Install | Late-2026 commissioning CTV/CSOV from Łeba |
Baltica 2 Ørsted / PGE (50/50) | Install | FOW WTIV hull not named (one of Terns) spring 2027; Cadeler WTIV hull not named 2027; array/export T&I not disclosed |
CVOW Commercial Dominion Energy | Install (delayed) | Jones Act CTV/SOV/guard/barge around remaining ~145 WTG + ~89 IAC through 2027 |
Dogger Bank B SSE Renewables / Equinor / Vårgrønn | Install | Second WTIV already contracted; watch commissioning SOV/CTV through Q2 2027 |
Dogger Bank C SSE Renewables / Equinor / Vårgrønn | Install | WTG hull timing vs DBB overlap; IAC support/guard through Aug 2026 |
East Anglia THREE ScottishPower Renewables (Iberdrola) / Masdar | Install | Cable-lay still running into late 2026 per developer |
Empire Wind 1 Equinor | Install | Jones Act CTV/guard/barge around first-of-class WTIV campaign |
Gennaker Skyborn Renewables + Stadtwerke München 25% | FID | Open residual support / CTV / guard unknown post-FC; major T&I packages already named 2025 — do not re-log as awards |
Hai Long 3 Northland Power / Gentari / Mitsui | Install | Commissioning CSOV/CTV into 2027 |
Hollandse Kust West VI (Ecowende) Shell / Eneco / Chubu Electric Power | Install | Late-2026 commissioning CTV/SOV if not already covered |
Hornsea 3 Ørsted (Apollo-managed funds co-owner) | Install | Construction SOV/CTV/guard around 197-MP + WTG campaign through 2027 |
Inch Cape ESB / Red Rock Renewables | Install | Which Cadeler M-class (Wind Maker vs Wind Mover) for Q4 2026; jacket/pin-pile vessel unnamed; guard/CTV through 2027 |
Nordlicht I Vattenfall (51%) / BASF (49%) | Install | Which DEME/Havfram WTIV for summer 2027; CSOV/SOV for WTG campaign not disclosed |
Nordlicht II Vattenfall (51%) / BASF (49%) | FID | Which WTIV hull summer 2028; CSOV/SOV and export package not disclosed |
Nordseecluster A RWE (51%) / NBIM (49%) | Install | Commissioning SOV/CTV into early 2027 |
Nordseecluster B RWE (51%) / NBIM (49%) | FID | WTG T&I contractor and hull not disclosed for 2028 60x 15 MW |
OranjeWind (Hollandse Kust West VII) RWE / TotalEnergies | Install | Voltaire also on Dogger Bank B to Q2 2027 — 2027 WTG slot tightness; construction CSOV before Purus O&M |
Revolution Wind Ørsted / Skyborn Renewables | Install | Last four WTG + commissioning CTV/SOV this month–Q4 |
Sunrise Wind Ørsted | Install | Jones Act support/CTV/guard while Scylla splits time with Revolution Wind |
Thor RWE (51%) / Norges Bank Investment Management (49%) | Install | FOW hull freed after Thor — next fixture |
Waterkant Luxcara / Waterkant Energy | Install | Which DEME/Havfram hull (Norse Wind vs Norse Energi) for spring 2028; foundation/cable/SOV not disclosed |
Windanker Iberdrola (51%) / Kansai (49%) | Install | Norse Energi due Hornsea 3 Q3 2026 — Windanker WTG must finish or overlap |
Zeevonk (IJmuiden Ver Beta phase 1) Vattenfall / CIP (Zeevonk II) | FID pending | WTG T&I not awarded; array/export/SOV open; 2028 window is the call |