East Anglia THREE

ScottishPower Renewables (Iberdrola) / Masdar

Install
Schedule
install
Install window
Turbines from Mar 2026; campaign to Q3/Q4 2026 (95 WTG)
COD / first power
Full COD Dec 2026 (first turbine Apr 2026)
Open vessel demand
What is still unnamed on this farm.

Cable-lay still running into late 2026 per developer

Who to call: ScottishPower Renewables / Cadeler / Masdar
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Seaway7 (Seaway Ventus; foundations complete)
Turbine T&I
Cadeler
Array cable
not disclosed
Export cable
not disclosed
O&M / SOV contractor
not disclosed
Fixtures & open campaigns on this farm
8 lines from the wind fixture book.
DateHullClassStatus
2026-04Wind Pace
Cadeler
WTIV / installationIn-house
covered
2026-03-18Wind Osprey
Cadeler
WTIV / installationIn-house
covered
2025-04-22NR Rebellion
NR Marine Services
CTVCovered
covered — construction charter
2025-04-22NR Hunter
NR Marine Services
CTVCovered
covered — construction charter
2025-04-22Tess
OEG
Guard / supportCovered
covered — guard charter
2024-05-29Grampian Kestrel
North Star
CSOVCovered
covered — bridge charter
2024-05-24Unnamed North Star VARD 4 19 newbuild (later Grampian Excelsior)
North Star
SOVCovered
covered — long-term O&M charter
2022-06-16Unnamed Seaway7 vessel(s)
Seaway7
CLV / cableCovered
Letter of exclusivity / preferred bidder; subject to FID; USD 500–750m
Source: OffshoreWIND.biz 3 Mar 2026; Cadeler / Masdar 21 Apr 2026; Energymagz foundation-complete updateoffshorewind.bizLogged 2026-08-14