SSY Offshore Wind Portal
Wind farms
Poland Baltic

Baltic Power

ORLEN / Northland Power

Install
Schedule
install
Install window
Remaining ~22–26 of 76 Vestas 15 MW (Wind Mover from Apr 2026); cables finishing
COD / first power
First power Jul 2026; construction complete autumn / 2H 2026
Open vessel demand
What is still unnamed on this farm.

Late-2026 commissioning CTV/CSOV from Łeba

Who to call: ORLEN / Northland / Cadeler
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Van Oord (Svanen MP) + SAL Lone (TP)
Turbine T&I
Cadeler
Array cable
not disclosed
Export cable
not disclosed
O&M / SOV contractor
Føn Energy Services (BoP O&M)
Fixtures & open campaigns on this farm
2 lines from the wind fixture book.
DateHullClassStatus
2026-04Wind Mover
Cadeler
WTIV / installationIn-house
covered
2023-07-03Unnamed Cadeler O-class vessel
Cadeler
WTIV / installationCovered
covered — turbine installation
Source: portalstoczniowy 50-turbine update; Energy Global 13 Jul 2026; OffshoreWIND.biz 14 Apr 2026energyglobal.comLogged 2026-08-14