Poland Baltic
Baltica 2
Ørsted / PGE (50/50)
Install
Schedule
install — MP complete 2026-08-21
Install window
MP campaign complete 2026-08-21 (111 MP: 107 WTG + 4 OSS; Van Oord Aeolus + Svanen own plant); 107 WTG in 2027 (FOW spring 2027 lot + Cadeler lot)
COD / first power
First power 1H 2027; full COD end-2027
Open vessel demand
What is still unnamed on this farm.
FOW WTIV hull not named (one of Terns) spring 2027; Cadeler WTIV hull not named 2027; array/export T&I not disclosed
Who to call: Ørsted/PGE Baltica marine / FOW / Cadeler
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Van Oord (Aeolus + Svanen)
Turbine T&I
Fred. Olsen Windcarrier (48 WTG) + Cadeler (balance)
Array cable
not disclosed
Export cable
not disclosed
O&M / SOV contractor
Pelagic + Bernhard Schulte CSOVs (construction/early O&M)
Named vessels
4 hulls stamped on this farm.
Fixtures & open campaigns on this farm
4 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2027-spring | unnamed (one FOW jack-up) Fred. Olsen Windcarrier | WTIV / installation | Fred. Olsen Windcarrier (Ørsted/PGE) | 48 WTG from spring 2027 | Open — pitch pitch — which Tern |
| 2027 | unnamed (Cadeler unit) Cadeler | WTIV / installation | Cadeler (Ørsted/PGE) | Balance of 107 WTG in 2027 | Open — pitch pitch — which hull |
| 2026-12 | Windea Clarke Bernhard Schulte | CSOV | Bernhard Schulte (Ørsted/PGE) | Dec 2026 / Feb 2027 start to Jul 2027 + options | Covered covered |
| 2026-10 | Pelagic Walu Pelagic | CSOV | Pelagic Wind Services (Ørsted/PGE) | Oct 2026 / Jan 2027 start to Nov/Dec 2027 + options | Covered covered |
Source: Van Oord 21 Aug 2026 MP complete; Ørsted 2026-05 start; OffshoreWIND.biz 6 Aug 2026 CSOVoffshorewind.bizLogged 2026-09-14