SSY Offshore Wind Portal
Wind farms
Taiwan Strait

Hai Long 3

Northland Power / Gentari / Mitsui

Install
Schedule
install
Install window
36x SG 14-222 from Mar 2026 (Sea Challenger); jackets done 2025
COD / first power
Project COD 2027 (2A grid-connected end-2025; 2B WTG in 2025)
Open vessel demand
What is still unnamed on this farm.

Commissioning CSOV/CTV into 2027

Who to call: Northland Power / CDWE
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
CDWE (Green Jade; jackets done)
Turbine T&I
CDWE (Sea Challenger)
Array cable
Seaway7 (Skandi Connector; IAC+export done)
Export cable
Seaway7
O&M / SOV contractor
not disclosed
Fixtures & open campaigns on this farm
2 lines from the wind fixture book.
DateHullClassStatus
2026-03-20Sea Challenger
CDWE / DEME
WTIV / installationIn-house
covered
2024-02-14Unnamed Cyan Renewables newbuild SOV
Cyan Renewables
SOVCovered
covered — long-term O&M charter
Source: OffshoreWIND.biz 20 Mar 2026; Seaway7 completion postoffshorewind.bizLogged 2026-08-14