Taiwan Strait
Hai Long 3
Northland Power / Gentari / Mitsui
Install
Schedule
install
Install window
36x SG 14-222 from Mar 2026 (Sea Challenger); jackets done 2025
COD / first power
Project COD 2027 (2A grid-connected end-2025; 2B WTG in 2025)
Open vessel demand
What is still unnamed on this farm.
Commissioning CSOV/CTV into 2027
Who to call: Northland Power / CDWE
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
CDWE (Green Jade; jackets done)
Turbine T&I
CDWE (Sea Challenger)
Array cable
Seaway7 (Skandi Connector; IAC+export done)
Export cable
Seaway7
O&M / SOV contractor
not disclosed
Named vessels
4 hulls stamped on this farm.
Fixtures & open campaigns on this farm
2 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2026-03-20 | Sea Challenger CDWE / DEME | WTIV / installation | CDWE | 36x SG 14 MW from Mar 2026 | In-house covered |
| 2024-02-14 | Unnamed Cyan Renewables newbuild SOV Cyan Renewables | SOV | Siemens Gamesa | 15 years from 2026 | Covered covered — long-term O&M charter |