US New York (east of Montauk)
Sunrise Wind
Ørsted
Install
Schedule
install
Install window
84x SG 11 MW from late Mar 2026 (Wind Scylla)
COD / first power
First power end-2026; full COD 2H 2027
Open vessel demand
What is still unnamed on this farm.
Jones Act support/CTV/guard while Scylla splits time with Revolution Wind
Who to call: Ørsted US Northeast marine / Cadeler
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
not disclosed
Turbine T&I
Cadeler (Wind Scylla)
Array cable
not disclosed
Export cable
Jan De Nul (Connector; Adhémar de Saint-Venant trench)
O&M / SOV contractor
not disclosed
Named vessels
4 hulls stamped on this farm.
Fixtures & open campaigns on this farm
1 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2026-03-25 | Wind Scylla Cadeler | WTIV / installation | Cadeler (Ørsted) | 84x 11 MW from late Mar 2026 | In-house watch — shared with Revolution Wind |