US New York Bight
Empire Wind 1
Equinor
Install
Schedule
install
Install window
54x Vestas 15 MW on Maersk Viridis from 2026 (vessel sailed Mar 2026); Kirby Jones Act feeders
COD / first power
First power late 2026; full COD 2027
Open vessel demand
What is still unnamed on this farm.
Jones Act CTV/guard/barge around first-of-class WTIV campaign
Who to call: Equinor Empire Wind / Maersk Offshore Wind / Kirby
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
not disclosed
Turbine T&I
Maersk Offshore Wind (Maersk Viridis) + Kirby Offshore Wind feeders
Array cable
not disclosed
Export cable
Nexans
O&M / SOV contractor
not disclosed
Named vessels
2 hulls stamped on this farm.
Maersk ViridisWTIV / installationKirby tugs/barges
Fixtures & open campaigns on this farm
3 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2026-03 | Maersk Viridis Maersk Offshore Wind | WTIV / installation | Equinor / Maersk Offshore Wind | 54x 15 MW from 2026; first power late 2026 | Covered covered — Jones Act feeders Kirby |
| 2022-05-13 | Unnamed newbuild Edison Chouest Offshore | SOV | Equinor / BP | 10 years from mid-2020s | Covered Firm |
| 2022-03-29 | Unnamed Maersk Supply Service newbuild Maersk Supply Service | WTIV / installation | Equinor / BP | Mid-2020s | Covered Firm |