Wind farms
German Baltic (Rügen)

Windanker

Iberdrola (51%) / Kansai (49%)

Install
Schedule
install
Install window
21x SG 14-236 from Jun 2026 (Norse Energi); MP+IAC done 2025
COD / first power
Complete end-2026; COD 2026 Q4–2027
Open vessel demand
What is still unnamed on this farm.

Norse Energi due Hornsea 3 Q3 2026 — Windanker WTG must finish or overlap

Who to call: Iberdrola / DEME
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Van Oord (Svanen)
Turbine T&I
DEME (ex-Havfram 2024 award)
Array cable
Van Oord
Export cable
not disclosed
O&M / SOV contractor
not disclosed
Named vessels
2 hulls stamped on this farm.
Fixtures & open campaigns on this farm
1 lines from the wind fixture book.
DateHullClassStatus
2026-06Norse Energi
DEME
WTIV / installationIn-house
watch — then Hornsea 3 Q3
Source: OffshoreWIND.biz 10 Jun 2026; iberdrola.com Windanker; DEME 13 May 2026offshorewind.bizLogged 2026-08-14