UK North Sea
Dogger Bank B
SSE Renewables / Equinor / Vårgrønn
Install
Schedule
install
Install window
WTG from Feb 2026 to ~Q2 2027 (95x Haliade-X 13 MW)
COD / first power
Full farm COD 2027 (phase B follows A)
Open vessel demand
What is still unnamed on this farm.
Second WTIV already contracted; watch commissioning SOV/CTV through Q2 2027
Who to call: SSE Renewables / Equinor Dogger Bank marine / Jan De Nul / Seaway7
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Seaway7 (foundations substantially complete)
Turbine T&I
Jan De Nul (Voltaire) + Seaway7 (Seaway Ventus from mid-2026)
Array cable
not disclosed
Export cable
not disclosed
O&M / SOV contractor
IWS Skywalker (commissioning SOV)
Named vessels
3 hulls stamped on this farm.
Fixtures & open campaigns on this farm
4 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2026-02-21 | Voltaire Jan De Nul | WTIV / installation | Jan De Nul | 21 Feb 2026 to ~Q2 2027 (95 WTG) | In-house covered |
| 2025-02-10 | IWS Starwalker IWS Fleet | CSOV | Dogger Bank Wind Farm | New contract commenced 10 Feb 2025; end not disclosed | Covered covered — new charter |
| 2025-01 | IWS Skywalker IWS Fleet | CSOV | Dogger Bank Wind Farm | Extended from end-Q2 2026 into Q3 2027 | Covered covered — extension |
| 2023-02-09 | Edda Boreas Edda Wind | CSOV | Dogger Bank Wind Farm consortium | Minimum two years from May 2023 | Covered covered — commissioning charter |
Source: Dogger Bank NtM 16 Feb 2026; SSE/Seaway7 contract; OffshoreWIND.biz 9 Jun 2026doggerbank.comLogged 2026-08-14