SSY Offshore Wind Portal
Wind farms
UK North Sea (Scotland)

Inch Cape

ESB / Red Rock Renewables

Install
Schedule
install
Install window
54 MP+TP done; 18 jackets + 54 pin piles 2026; IAC from Jul 2026; WTG Q4 2026 ~249 days
COD / first power
First power late 2026; full COD 2027
Open vessel demand
What is still unnamed on this farm.

Which Cadeler M-class (Wind Maker vs Wind Mover) for Q4 2026; jacket/pin-pile vessel unnamed; guard/CTV through 2027

Who to call: Inch Cape marine / Cadeler / N-Sea / ESB
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Jan De Nul Les Alizés (54 MP; done) + Seaway7 Alfa Lift (54 TP; done). Jacket/pin-pile T&I not named
Turbine T&I
Cadeler (one M-class; hull not allocated)
Array cable
N-Sea
Export cable
Enshore Subsea (export lay done; jointing through end-2026)
O&M / SOV contractor
not disclosed
Fixtures & open campaigns on this farm
4 lines from the wind fixture book.
DateHullClassStatus
2026-Q4unnamed (one Cadeler M-class)
Cadeler
WTIV / installationOpen — pitch
pitch — Maker vs Mover
2026-07-31Altera
N-Sea
CLV / cableCovered
covered
2026-07-17Olympic Taurus
SOVCovered
covered
2026unnamed
Foundation spreadOpen — pitch
pitch — jacket spread not named
Source: inchcapewind.com TP complete Aug 2026; NtM 17/2026; Cadeler 24 Jun 2024; OffshoreWIND.biz 3 Jul 2026inchcapewind.comLogged 2026-08-14